traffic on the gardiner expressway will be further complicated as the highway’s rehabilitation plan continues into 2025. the city of toronto has announced the next stage of the gardiner expressway strategic rehabilitation plan, which will see repair work done on five bridges this coming spring.
repair work will begin on the five bridges in section 3 of the gardiner expressway, which runs from hwy. 27 to the humber river. the bridges get a head start on section 3 after critical repairs were needed after a condition assessment was conducted.
section 3 of the highway plan is scheduled to take place between 2027 and 2031. repair on the five bridges will need to be done ahead of the projected timeline.
the gardiner overpasses at park lawn rd. and mimico creek, along with the westbound on-ramp from park lawn rd. over mimico creek, will be fully replaced. repairs will be made to the kipling ave. and islington ave. bridges over the gardiner expressway.
bridge repair work is slated to begin in spring 2025 with a slight pause from may to july 2026 to accommodate anticipated increased traffic during fifa world cup events in toronto.
work is expected to be finished by december 2026.
during the construction, lane and ramp restrictions are expected in the following areas: